The new plant uses a Hoval gas condensing boiler with an output of 750 kW. The Hoval control system manages a total of ten heating circuits across both buildings. In addition to the new central plant room, we built the substation in the second building and integrated it into the overall system via the district heating line. The new gas supply was also part of our scope: we calculated and planned the gas line and implemented it in cooperation with the responsible gas utility. From system sizing and hydraulic design to controls and construction, the complete plant concept was delivered from a single source. We have also maintained and serviced the entire system for several years.