Heat Pump, PVT and Battery Working Together

Chürzistrasse, 8600 Dübendorf
PV and PVT rooftop installation at Chürzistrasse in Dübendorf
Project Description

Solar heat boosts heat pump output

At Chürzistrasse in Dübendorf, we replaced a 75 kW gas heating system with a 42 kW heat pump connected to water-filled borehole heat exchangers. The key is its integration with hybrid PVT collectors: alongside solar electricity, they provide heat and can raise the temperature in the borehole circuit to as much as 23 °C. Under these conditions, the heat pump delivers more than 55 kW of heating output. The hydraulic integration also enables free cooling in summer. Individual preferences are accommodated: one apartment is specifically excluded from free cooling during cooling operation, with the necessary data transmitted over the internet. Our own team developed the complete system concept and handled planning and installation without an external engineering consultancy.

Fronius inverter for the 25 kWp photovoltaic system installed by our own team
Project Description

Store and distribute solar power, with Loxone control

The photovoltaic system we installed has a capacity of 25 kWp. In a second stage, we added a battery with 55 kWh of storage capacity. The building also has a vZEV arrangement, allowing electricity to be billed directly to tenants. We implemented system visualisation and battery management using Loxone. Heating, summer cooling, solar electricity and battery storage work together as a coordinated system.

Loxone control cabinet for system visualisation and battery management at Chürzistrasse

More Projects
from us

All Projects
Concealed air-conditioning system with two discreet air outlets in a sloping roof

Cooling Technology Where Standard Doesn't Fit

Three properties, three unusual installation situations: a unit without a suitable rear wall, a recessed ceiling cassette and a concealed installation in a sloping roof. We planned each solution individually and coordinated all other trades involved.

New NIBE heat pump installed on a small plinth in a plant room in Zumikon

Heating, Hot Water and Cooling in a Tight Space

In Zumikon, we replaced the existing heat pump with the appropriate NIBE successor model. The new unit had to continue providing heating, domestic hot water and cooling from a very small plinth – and we also brought the faulty wine-cooling unit back into operation.

Air-to-water heat pump on the roof of an apartment building in Bassersdorf

Heat Pump Repaired, Existing System Retained

In an eight-apartment building in Bassersdorf, the heat pump failed after compressor damage. Targeted repairs and hydronic improvements allowed the existing system to remain in use.

Air-to-water heat pump in a family home on Lägernstrasse in Dübendorf

Family Home Heating Replacement with a Heat Pump

In a typical family-home neighbourhood in Dübendorf, we replace existing oil and gas heating systems with properly sized air-to-water heat pumps and coordinate the entire project.

Twin pellet boiler system with two ETA ePE-K 240 boilers in Uster

When a Heat Pump Won't Do: 480 kW from Pellets

For a listed property with annual gas consumption of around 1 million kWh, our feasibility study led to a 480 kW twin-boiler pellet heating system.

Hydraulic schematic of the new heat pump system in Zollikon

Heating for House and Pool, Cooling for the Building

At a property in Zollikon, the existing heat pump caused problems with domestic hot water, pool heating and free cooling. A new ground-source heat pump and redesigned hydronics allow these functions to operate simultaneously.

Eight Heat Pumps on One Shared Borehole Field

Four semi-detached apartment buildings in Dübendorf relied on an ageing central oil boiler. We installed four decentralised plant rooms with eight ground-source heat pumps sharing a field of 27 boreholes.

750 kW Hoval gas condensing boiler at Industriestrasse in Dietlikon

750 kW of Heating for Two Commercial Buildings

An ageing Viessmann twin oil-boiler system was replaced by a 750 kW Hoval gas condensing boiler. The new control system serves ten heating circuits across two buildings.

Two Buildings, Two Independent Ground-Source Systems

Two apartment buildings in Fällanden shared an oil heating system. Following a feasibility study, we replaced it with two fully independent ground-source heat pump systems, each with its own domestic hot water preparation.

New heating system on MS Helvetia on Lake Zurich

A New Heating System for MS Helvetia

Zürichsee-Schifffahrtsgesellschaft commissioned us to replace the diesel heating system on MS Helvetia. At the same time, we solved the uneven heat distribution on board.

Pellet heating system for the church building in Schwerzenbach

Pellet Heating for a Church and Residential Building

For the new church building in Schwerzenbach, we worked with the specialist planner to install a pellet heating system combining different heat distribution systems and domestic hot water preparation.

75 kW air-to-water heat pump serving two apartment buildings in Gutenswil

75 kW from the Air for Two Apartment Buildings

Two apartment buildings in Gutenswil shared a 75 kW oil boiler, but geothermal boreholes could not be approved. We replaced the oil boiler with a 75 kW air-to-water heat pump for heating and domestic hot water.

Central plant of the private district heating network in Freudwil

A Private District Heating Network for Freudwil

Two Fröling wood-chip boilers with outputs of 150 and 60 kW supply houses and apartment buildings in Freudwil through a private district heating network. We installed the central plant, substations and complete connections for the individual heat consumers.

Completed bathroom renovation at Frickenstrasse in Dübendorf

Bathroom Renovation from a Single Source

For this bathroom renovation in Dübendorf, we handled the complete planning, supply and coordination of the work involved – from product selection to the finished bathroom.

Cascade of two Alpha innoTec air-to-water heat pumps in Brüttisellen

Cooling with Heat Pumps, Saving Gas in Winter

For a commercial property in Brüttisellen, we supplemented the existing gas heating system with two Alpha innoTec air-to-water heat pumps. They provide around 40 kW of cooling in summer and reduce gas consumption in winter.

Contact us
now

Do you have a project that requires expertise? We are ready to answer your questions and work with you to find the best solution for your needs. Don't hesitate to contact us today to learn more about our services.

Contact us now